PARTIAL LIST OF POWER AND UTILITIES
PROJECTS
|
|
No. |
Item |
Capacity of Unit |
Control System |
Status |
Applications |
|
1 |
CCS for #1 Unit of
Shiheng Power Plant of Shandong Province |
300MW |
SPEC200 |
Starting 1987.1 |
CCS |
|
2 |
DAS for
#1 Unit of Shiheng Power Plant of Shandong Province |
300MW |
FOX 1/A |
Starting 1987.1 |
DAS |
|
3 |
DAS for
#1 Unit of Shiheng Power Plant of Shandong Province |
300MW |
SPEC200Micro |
Starting 1988.1 |
CCS |
|
4 |
DAS for
#1 Unit of Shiheng Power Plant of Shandong Province |
300MW |
FOX1/A |
Starting 1988.1 |
DAS |
|
5 |
BOP for
#2 Unit of Shiheng Power Plant of Shandong Province |
300MW |
SPEC200Micro |
Starting 1988.1 |
BOP |
|
6 |
Power
Station of Baotou Textile Mill |
3 Boilers,
2
Turbines |
Intellegient Controller |
Starting 1989 |
Control
Systems for Boiler, Turbine &
Auxiliaries |
|
7 |
Hepo
Power Plant of Shanxi Provincce |
2*50MW |
Hitachi
Single-loop Controller |
Starting 1990 |
Control
Systems for Boiler, Turbine &
Auxiliaries |
|
8 |
CCS for
#1 Unit of Pingwei Power Plant of Anhui Province |
600MW |
SPEC200Micro |
Starting 1990.1 |
CCS |
|
9 |
DAS for
#1 Unit of Pingwei Power Plant of Anhui Province |
600MW |
FOX1/A |
Starting 1990.1 |
DAS |
|
10 |
BOP for
#1 Unit of Pingwei Power Plant of Anhui Province |
600MW |
SPEC200Micro |
Starting 1990.1 |
BOP |
|
11 |
#2
Huaneng Shidongkou Power Plant |
2*600MW |
A-B
PLC-2 |
Starting 1992.12 |
Protecting System of Coal Feeder and Pulverizer |
|
13 |
#2
Huaneng Shidongkou Power Plant |
2*600MW |
Bailey
N-90 |
Starting 1992.12 |
DAS、DCS、FSSS |
|
14 |
#2
Huaneng Shidongkou Power Plant |
2*600MW |
Toshiba |
Starting 1992.12 |
Control
Systems of Air Compressor for Instrument use |
|
15 |
CCS for
Weifang Power Plant of Shandong Province |
300MW |
Network-90 |
Starting 1994.05 |
DAS、CCS |
|
16 |
Power
Station of Shanghai Pioneer Pharmaceutical Co. Ltd |
3 Boilers, 2 Turbines |
MicroMax2 |
Starting 1994.05 |
DAS、MCS |
|
17 |
Zhuhai
Cellulose Fibers Co. of Guangdong Province |
3 Boilers, 2
Turbines |
APACS |
Starting 1996.04 |
DAS、MCS |
|
18 |
Kunming
Cellulose Fibers Co. of Yunnan Province |
3 Boilers, 2
Turbines |
APACS |
Starting 1996.06 |
DAS、MCS |
|
19 |
#1 & #2
Units of Zhongshan Power plant of Guangdong Province |
2*125MW |
APACS |
Starting 1997.08 |
DAS、CCS、SCS、SOE |
|
20 |
Liulangdong Waterpower Station of Yunnan Province |
Waterpower Station |
APACS |
Starting 1997 |
DAS、MCS |
|
21 |
Gaoda
Newport Power Plant of Jiangsu Province |
Gas-Turbine |
APACS |
Starting 1997 |
DAS、MCS、Communication
with PLC |
|
22 |
Liaocheng Power Plant of Shandong Province |
1*100MW |
Moore352 Single-loop Controller |
Starting 1997.09 |
MCS |
|
23 |
#5 Unit
of Fulaerji General Power Plant of Heilongjiang Province |
1*200MW |
APACS |
Starting 1997.1 |
DAS、CCS、SCS、DEH、
Communication with MIS |
|
24 |
#3 Unit
of Harbin Power Plant of Heilongjiang Province |
1*200MW |
APACS |
Starting 1997.11 |
DAS、CCS、SCS、DEH、Communication with FSSS & MIS |
|
25 |
#6 Unit
of Fulaerji General Power Plant of Heilongjiang Province |
1*200MW |
APACS |
Starting 1998 |
DAS、CCS、SCS、DEH、Communication with FSSS & MIS |
|
26 |
#2 Unit
of Harbin Power Plant of Heilongjiang Province |
1*200MW |
APACS |
Starting 1998 |
DAS、CCS、SCS、DEH、Communication with FSSS & MIS |
|
27 |
#4 Unit
of Huangpu Power Plant of Guangdong Province |
1*125MW |
APACS |
Starting 1998 |
DAS、CCS、SCS、SOE |
|
28 |
#7 Unit
of Haikou Power Plant of Hainan Province |
1*125MW |
APACS |
Starting 1998 |
MCS |
|
29 |
#2 Unit
of Huangpu Power Plant of Guangdong Province |
1*125MW |
APACS |
Starting 1999 |
DAS、CCS、SCS、DEH、SOE Communication with FSSS & MIS |
|
30 |
Taicang
Huaneng Power Plant |
300MW |
348
FieldPac |
Starting 1999.01 |
BOP |
|
31 |
Wudangshan Waterpower Plant |
3*2500MW |
Euro |
Starting 1999.12 |
|
|
32 |
#5 Unit
of Daqin Huaneng Power Plant of Heilongjiang Province |
200MW |
APACS |
Starting 2000 |
DAS、MCS、SCS、FSSS、Communication
with DEH |
|
33 |
Xutang
Power Plant of Jiangsu Province |
2*300MW |
348
FieldPac |
Starting 2001 |
BOP |
|
34 |
Xigu
Power Plant of Gansu Province |
50MW |
APACS |
Starting 2002 |
DAS、MCS、SCS |
|
35 |
Power
Plant of Benxi Iron & Steel Group |
75T/H |
APACS |
Starting 2002.12 |
DAS、MCS、SCS |
|
36 |
Power
Plant of Benxi Fanya Co. Ltd of Liaoning Province |
3 Boilers, 2
Turbines |
APACS |
Starting 2002.11 |
DAS、MCS、SCS |