PARTIAL LIST OF WATER TREATMENT PROJECTS OF POWER PLANT
|
|||||
|
No. |
Item |
User |
Control System |
Status |
Application |
|
1 |
Chemicals Adding |
Shiheng Power Plant |
SPEC200 |
Starting 1987.6 |
Design,Integration,Programming,Test |
|
2 |
Acid Adding of Circulating Water |
Shiheng Power Plant |
SPEC200 |
Starting 1987.6 |
Design,Integration,Programming,Test |
|
3 |
Make-up Water |
Pingwei Power Plant |
MODICON 584M |
Starting 1989.5 |
Programming,Test |
|
4 |
Sampling of Water & Steam |
Shiheng Power Plant |
SPEC200 |
Starting 1989.5 |
Programming,Test |
|
5 |
Waste Water |
Huaneng Shidongkou Power Plant |
A-B PLC 5/15 |
Starting1991.1 |
Test |
|
6 |
Make-up Water |
Huaneng Shidongkou Power Plant |
A-B PLC 5/15 |
Starting 1991.1 |
Test |
|
7 |
Water Pre-Treatment |
Huaneng Shidongkou Power Plant |
A-B PLC 5/15 |
Starting 1991.1 |
Test |
|
8 |
Chemicals Adding |
Huaneng Shidongkou Power Plant |
A-B PLC 5/15 |
Starting 1991.1 |
Test |
|
9 |
Chlorinf Adding of Circulating Water |
Huaneng Shidongkou Power Plant |
A-B PLC 5/15 |
Starting 1991.1 |
Test |
|
10 |
Sampling of Water & Steam |
Huaneng Shidongkou Power Plant |
A-B PLC 5/15 |
1991.1 |
Test |
|
11 |
Crude Water Treatment |
Wujing Power Plant |
Mitsibishi D Series |
1991.8 |
Design,Integration,Programming,Test |
|
12 |
Acid Adding of Circulating Water |
Huaneng Shidongkou Power Plant |
A-B PLC 5/15 |
1991.12 |
Test |
|
13 |
Anti-Infitration |
Huaneng Shidongkou Power Plant |
A-B PLC 5/15 |
1991.12 |
Test |
|
14 |
Condensate |
Wujing Power Plant |
MODICON 984-680 |
1992.4 |
Design,Integration,Programming,Test |
|
15 |
Waste Water |
Wujing Power Plant |
MODICON 984-680 |
1992.4 |
Design,Integration,Programming,Test |
|
16 |
Make-up Water |
Wujing Power Plant |
MODICON 984-680 |
1992.4 |
Design,Integration,Programming,Test |
|
17 |
Make-up Water |
Qishuyan Power Plant |
Mitsbishi F Series |
1992.7 |
Design,Integration,Programming,Test |
|
18 |
Pure Waater Station |
Jinshan Petrochemical Plant |
MODICON 984-680 |
1992.11 |
Design,Integration,Programming,Test |
|
19 |
Periodic Drain of Boiler |
Nantong Cellulose Fibers Co. |
TEXAS T1-545 |
Starting 1993.1 |
Design,Integration,Programming,Test |
|
20 |
Make-up Water |
Nantong Cellulose Fibers Co. |
TEXAS T1-545 |
Starting 1993.6 |
Design,Integration,Programming,Test |
|
21 |
Air Cooling of Circulating Water |
Datong #2 Power Plant |
A3ACPU |
Starting 1993.6 |
Design,Integration,Programming,Test |
|
22 |
Runback Control System |
Nantong Cellulose Fibers Co. |
TEXAS T1-545 |
Starting 1994.9 |
Design,Integration,Programming,Test |
|
23 |
Make-up Water |
Waigaoqiao Power Plant |
MODICON E984-685 |
Starting 1995.4 |
Design,Integration,Programming,Test |
|
24 |
Condensate |
Maanshan #2 Power Plant |
MODICON E984-686 |
Starting 1995.12 |
Design,Integration,Programming,Test |
|
25 |
Make-up Water |
Mozafago Power Plant of Pakistan |
MODICON E984-687 |
Starting 1996 |
Design,Integration,Programming,Test |
|
26 |
Condensate |
Mozafago Power Plant of Pakistan |
MODICON E984-688 |
Starting 1996 |
Design,Integration,Programming,Test |
|
27 |
Industrial Service Water |
Ezhou Power Plant |
OMRON C1000H |
Starting 1996 |
Design,Integration,Programming,Test |
|
28 |
Make-up Water |
Power Station of Zhonhua Paper Mill |
Siemens S-115U |
Starting 1996 |
Design,Integration,Programming,Test |
|
29 |
Industrial Waste Water |
Ezhou Power Plant |
sPEC200 |
Starting 1996.4 |
Design,Integration,Programming,Test |
|
30 |
Make-up Water |
Gas Turbine Unit of Huarui Power Plant |
B&R 2005 |
Starting 1997 |
Design,Integration,Programming,Test |
|
31 |
Pump Room of Circulating Water |
Zhongshan Power Plant |
COMPACK PC130 |
Starting 1997 |
Design,Integration,Programming,Test |
|
32 |
Boiler & Service Water |
Shanghai Waigaoqiao Qiba |
MODICON PC225 |
Starting 1997.1 |
Design,Integration,Programming,Test |
|
33 |
Make-up Water |
MALCD Power Plang of India |
GE 90 |
Starting 1999.3 |
Design,Integration,Programming,Test |
|
34 |
Dearator & Feedwater of Boile |
Power Plant of Meishan MetallurgicalCo. |
|
Starting 2000.3 |
Design,Integration,Test |
|
35 |
Waste Water |
Zhangzhou Houshi Powr Plant |
AB PLC 5/40E |
Starting 2000.3 |
Design,Integration,Programming,Test |
|
36 |
Make-up Water |
Wenzhou #2 Power Plant |
MODICON QUANTUM |
Starting 2000.4 |
Design,Integration,Programming,Test |
|
37 |
Make-up Water |
Nantong Cellulose Fibers Co. |
TEXAS T1-545 |
Starting 2000 |
Design,Integration,Programming,Test |
|
38 |
Waste Water & Circulating Water |
Xutang Power Co.Ltd |
|
Starting 2001 |
Integration |
|
39 |
Periodic Drain of Boiler |
Huibei #2 Power Plant |
MODICON E984-385 |
Starting 2000.4 |
Design,Integration,Programming,Test |
|
40 |
Make-up & Waste Water |
Iraq Gas Turbine Unit |
MODICON QUANTUM |
Starting 2001.1 |
Design,Integration,Programming,Test |
|
41 |
Make-up Water |
Shangdong Zhangqiu Power Plant |
MODICON QUANTUM |
Starting 2002.2 |
Design,Integration,Programming,Test |
|
42 |
Make-up Water |
Shangdong Liyan Power Plant |
MODICON QUANTUM |
Starting 2003.3 |
Design,Integration,Programming,Test |
|
43 |
Pump Room of Circulating Water |
Jiaxing Power Plant |
MODICON QUANTUM |
Starting 2003.8 |
Design,Integration,Programming,Test |
|
44 |
Condensate |
Huangshi Power Plant |
AB PLC 5/40E |
Starting 2003 |
Design,Integration,Programming,Test |
|
45 |
Centrialized Control of Water Zone |
Jiawang Power Plant of Jiangsu Province |
MODICON QUANTUM |
Starting 2003 |
Design,Integration,Programming,Test |